Demo Project Bid Leveling Sheets Can Make All the Difference

use of a checklist during the bidding process

One of the keys to a successful demolition or selective demolition project outcome is the development and use of a checklist during the bidding process known as the leveling sheet. The leveling sheet defines the scope of the project in minute detail, spelling out exactly what is included or excluded in each demolition contractor’s proposal and effectively leveling the bids for a fair comparison. Without a leveling sheet, items can go unidentified, leading to an array of problems, change orders, delays, finger-pointing, and all-around hard feelings between client and contractor.

Leveling sheet specifications on a demolition project might include:

Will demolition equipment used be battery operated or diesel?

Environmental hazards such as asbestos, lead paint, or old tanks – will they be remediated, and how?

Is the project union or non-union, and what are the working hours? Will there be second and third shifts?

Will dust and vibration be limited to specific hours?

Asset recovery – are there items of value such as copper wire or salvageable equipment that can offset project costs?

Will the demolition contractor use subcontractors to perform electrical, plumbing or mechanical aspects of their project?

Does the demolition project include specific safety items such as ISNetworld, VPPP, HAZWOPER, etc.?

Using a leveling sheet to identify what is included or excluded on any demolition or select demolition project can ensure that equipment and services are purchased wholesale from the outset, not at retail prices after the fact. Doing your homework can save a lot of money and streamline your demolition project.

R. Baker & Son - All Industrial Service
1 Globe Court
Red Bank, NJ 07701
http://www.rbaker.com

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Precision Chiller Dismantling & Mechanical Retrofit Case Study
Precision Chiller Dismantling & Mechanical Retrofit Case Study

A local New Jersey representative for a major chiller manufacturer recommended R. Baker & Son for a demanding chiller change-out project. The scope: remove two 1,200-ton chillers and their...
Discover how a custom negative pressure wall and real-time monitoring protected a pharmaceutical cleanroom during high-stakes facility demolition.
How to Protect Active Cleanrooms During Demolition: A Negative Pressure Wall Case Study

Protecting a client's environment during demolition and renovation work has always been part of what we do at R. Baker & Son. Anyone in the industry knows ICRA protection, the barrier system...
rigging medical equipment into a hospital - R. Baker & Son
Just-in-Time Rigging Keeps a Hospital Running During a Critical Enabling Project

R. Baker & Son received a call from a concerned South Jersey mechanical contractor facing a complex rigging project on a tight deadline. Another rigging contractor had passed on the job late in...
Riggers assembling tower crane sections during construction - R. Baker & Son - Master Riggers.
How Mobile and Tower Cranes Are Assembled & Dismantled

Mobile cranes come in many styles, shapes, and sizes, with the hydraulic crane and the luffing jib being the most common. R. Baker & Son has worked with just about every mobile crane on the...
Demolition concrete debris fed into an industrial crusher for recycling
7 Ways Demolition Protects Communities & the Planet

7 Ways Demolition Builds Better Communities -And Why It Matters When most people picture demolition, they see dust clouds and falling walls. What they don't see is the careful planning,...
R. Baker & Son industrial contractors executing mission-critical transformer replacement with rigging equipment at medical facility
How R. Baker & Son Executes High-Stakes Projects with Engineered Work Plans

Mission-critical and high-stakes projects demand detailed, preplanned coordination to ensure success at every level. When it comes to plant shutdowns, startups, repairs, changeovers, and equipment...
R. Baker & Son rigging team performing final precision positioning and alignment of a multi-ton medical MRI magnet onto its concrete anchoring pad inside a specialized hospital imaging room.
MRI & Medical Imaging Equipment Rigging: A Turnkey Installation Case Study

Medical equipment rigging and installation requires a specialized approach to protect high-value, delicate assets. At R. Baker, we successfully navigate these complex rigging projects using...
R. Baker and son welding on complex hospital demolition job
Hospital Boiler Room Demolition: Removing Steam Boilers and Mechanical Equipment

R. Baker & Son was tasked with a complex demolition project at an active hospital, systematically removing two aging Cleaver-Brooks steam boilers (a 350 HP and a 200 HP unit), along with an...