asset recovery, rigging team with sling and interior demolition

Rigging Plan Consulting and Estimating

planning and estimation stages - rigging company

On construction and renovation projects that include installation or relocation of equipment and/or building systems, construction managers and general contractors should consider consulting with an experienced rigging company like R. Baker & Son during the planning and estimation stages. CMs and GCs will often go it alone to determine how to move equipment into a building efficiently and on time, then estimate the cost to do so. The problem is that most are not aware of equipment and techniques available to riggers, nor do they have the ingenuity that comes from years of rigging experience. Tapping into R. Baker & Son’s vast rigging expertise could mean tens, or even hundreds, of thousands of dollars in cost savings as well as substantial time shaved off the overall project schedule, and it could make all the difference in project awards. 

Case in point, a CM firm had put together a project estimate and schedule for a pharmaceutical construction project, but had some doubts about using their own rigging and routing plan, so R. Baker & Son was called in to consult and provide rigging services. We quickly determined that, by adding two large skylights, building equipment including two chillers, several air handlers, compressed air, two boilers, and a waste neutralization system, could be rigged into the mechanical room more quickly and easily than original estimates. Additionally, the skylights would provide natural light in the mechanical rooms, reducing lighting and energy needs. 

R. Baker & Son’s revised rigging and routing plan also specified that process equipment including liquid and gas chromatographs, isolators, lyophilizers, autoclaves, and bioreactors could be hoisted and lowered down a freight elevator shaft to the first three floors of the building using a 130-ton crane with extended boom. The shaft was temporarily capped for access and protection from the weather, allowing timely installation of walls and floors by other trades. We also identified several doors that would need to be widened for future building maintenance and equipment replacement. 

Overall, R. Baker & Son’s new plan shaved five weeks and $260,000 from the CM’s original estimate.

About R. Baker & Son All Industrial Services

R. Baker & Son All Industrial Services, a Minority and Women-Owned Business Enterprise (M/WBE), in business since 1935, is a premier specialized contractor operating in the United States, Canada, and Puerto Rico, with over one hundred employees and an exemplary safety record (we have been directly involved in four sites that received VPP OSHA Safety Awards). R. Baker & Son is financially strong, with bonding capabilities of over $10 million. Capabilities include industrial and commercial demolition, rigging, machinery- and plant-moving, dismantling, decommissioning, plant and equipment relocation, interior demolition, selective demolition, warehousing, wrecking and razing, millwright, plant reconfigurations, heavy rigging, salvage, environmental services, remediation, decontamination, abatement, and investment and asset recovery.

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553

https://rbaker.com/

Full News Archive

2026

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

The finishing beam used in the process weighed 2,600 lbs and had to be perfectly parallel and level to the drum it was refinishing, both within less than 1/64 of an inch.
Industrial Drum Refinishing Support: A Custom Rigging and Structural Solution

When a manufacturer we had previously performed rigging assembly and installation work for returned more than a year later with a unique and complex challenge, they knew who to call. The company...
Air skates (air casters) lifting and moving multi-ton industrial equipment using compressed air in a plant relocation project
Air Skates: How to Move Multi Ton Loads Without Touching the Floor

Air skates, also known as air casters, air skids, or air dollies, are a specialized rigging solution that R. Baker & Son has deployed for many years to move heavy machinery, fragile equipment,...
demolition innovation in protection - substation, non metallic wire mesh,
Demolition Protection: Safeguarding People, Property & Critical Systems

What Demolition Protection Truly EntailsIn the complex world of demolition, protection goes far beyond basic safeguards. As therecognized leader in demolition protection, R. Baker & Son defines...
R. Baker & Son rigging crew performing pre-construction planning and heavy equipment rigging for demolition and industrial plant relocation project
Precon Services for Demolition, Rigging & Plant Relocation

For more than 90 years, R. Baker & Son has been delivering expert precon services for demolition, rigging, and industrial plant relocation projects. Before any construction work begins, our team...
Rigger working on R. Baker & Son - All Industrial Services. Welding.
Rigging, Assembly and BIM: Bridging the Gap

Prefabricated equipment and systems have become the standard for good reason. The more you can prefabricate, the faster, more cost-effective, and higher quality a project becomes. The goal is simple:...
Several large steam-to-hot-water heat exchangers
Quick Mobilization for Pilot Plant Dismantling and Demolition

When a building consolidation commitment required our client to dismantle and demolish a 30,000 square-foot pilot plant immediately, they turned to R. Baker & Son. Having rigged much of the...
Rigging, completely assembling, and setting 12 large fiberglass cylindrical tanks, each with a 17,000-gallon capacity.
Rising to a Rigging Challenge: Tank Installation in N. Philadelphia

The Project Scope As part of a major rigging project in North Philadelphia, R. Baker & Son faced a complex installation challenge: rigging, completely assembling, and setting 12 large...
Nine downflow booths carefully dismantled and packaged for refurbishment during pharmaceutical lab renovation.
Negative Pressure Demolition in an Active Pharmaceutical R&D Laboratory

R. Baker & Son had the unique opportunity to return to a pharmaceutical R&D laboratory project we had successfully completed years earlier, where our riggers and millwrights originally...