All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
 
All Industrial Services Inc. of New Jersey| 190 Boundary Rd, Marlboro, NJ 07746
quote@rbaker.com| 732-222-3553|         
190 Boundary Rd, Marlboro, NJ 07746 732-222-3553
asset recovery, rigging team with sling and interior demolition

Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Rigging NY and NJ icons, Statue of Liberty, R. Baker and Son
Rigging NYC and NJ - Most Iconic Structures with Expert Precision

For 90 years, R. Baker & Son has been a cornerstone of rigging services in New York and New Jersey, expertly undertaking complex lifting, moving, and safeguarding operations for some of the...
Telescopic crane lifting heavy equipment during a rigging project in NJ & NY
Why Telescopic Cranes Are Essential in Rigging Work

It is remarkable how innovation and technology continue to change and improve construction equipment. Manufacturers have evolved to create machinery that serves multiple purposes at job sites. A...
16,000-gallon mixing tanks, each with an 18-ft agitator with a 3-inch shaft
Expert Rigging and Maintenance for Industrial Mixing Tanks

A new client reached out to R. Baker for rigging services, regarding a challenging issue affecting their production and throughput. We were referred by an engineer with whom we had worked in the...
Vertical Water Curtains, The Future of Dust Control, Dustboss Water Cannon
Vertical Water Curtains: The Future of Dust Control in Urban Implosions

Many implosion demolition projects always make the news as it's impressive to see a perfectly timed implosion where the building literally falls into itself. The engineering behind it and the...
R. Baker Industrial Worker With Laptop At Demolition Project
Precision Planning in Construction Demolition

When it comes to defining a construction project's approach, most proficient project management teams can produce a plan that methodically lays out phases, tasks, and timelines in meticulous...
interior demolition at a manufacturing and production facility, rigging crew
Precision MEP Install at a South Jersey Manufacturing Facility

As part of a 150,000 sq/ft manufacturing and production facility renovation project in South Jersey, R Baker had completed the selective interior demolition work months before. This work included...
Precision Demolition Equipment
Precision Demolition: R. Baker & Son's Advanced Equipment & Techniques

When tackling the complexities of industrial demolition, you're not just swinging a wrecking ball. At R. Baker & Son, we understand that precision, safety, and efficiency are paramount....
R. Baker & Son Crane used in plant relocation
Comprehensive Guide to Plant Relocation: Planning for Success

Strategic Planning: The Foundation of Plant Relocation Plant relocation represents a complex logistical challenge where success hinges primarily on thorough planning. A comprehensive master plan...