Innovative Plan in Manhattan High Rise Project

56 Leonard Street

By the time construction of 56 Leonard, an iconic new residential skyscraper located in the Tribeca section of Manhattan, wrapped up late last year, all of its 145 luxury units had sold out, some going for prices as high as $48 million. Known as the Jenga Tower due to its stunning and unusual appearance, the glass-encased 60-story building features a staggered silhouette of shifting and varying floorplates, cantilevers, and balconies. Not surprisingly, construction of 56 Leonard was exceptionally complex, even by New York City standards, which was recognized last month when ENR New York named 56 Leonard 2017’s Best Project in the Residential/Hospitality category.  

R. Baker & Son took on one of the challenging project’s early hurdles: the removal of massive steel I-beams cantilevered 25 feet over the roof of an adjacent building. The falsework beams were installed on the 6th floor to provide temporary structural support until the concrete had sufficiently cured while construction progressed on the floors above. R. Baker & Son was challenged to develop an innovative plan to remove the huge beams safely and efficiently. Taking into account the many complex logistical challenges of the project, Baker engineers determined that beam sections would need to be cut and removed from the structure’s interior, rather from the exposed ends jutting from the building.  After hours of brainstorming, the Baker team came up with a unique and inventive solution that would provide the key to the project: custom-fabricated weighted dollies that would be used to slide the beams inward while serving as counterweights. 

The removal procedure began with Baker team members fabricating steel guides around each I-beam and securing them to nearby concrete columns. After attaching two heavily-weighted dollies to each beam, workers would cut a 4-foot section, each weighing 1,200 lbs., from the interior end of the I-beam. The dollies/counterweights prevented the cantilevered ends of the beams from tipping past the fulcrum point when the sections were detached. Each time a section was removed, Baker crew members used heavy-duty winches to wheel the remaining beam another four feet into the building. Then everything would be repositioned and the entire process would be repeated. The removed sections were stacked three high, and workers utilized an in-house material hoist to lower the 3,600-lb. stacks to ground level. 

R. Baker & Son - All Industrial Services
190 Boundary Road
Marlboro, NJ 07746
732-222-3553http://rbaker.com/demolition-contractors-new-jersey.php

Full News Archive

2025

2024

2023

2022

2021

2020

2019

2018

2017

2016

2015

2014

2013

2012

2011

2010

2009

2008

Recent News

Rigging equipment ready for a heavy lift, NYC, NJ
Industrial Rigging NYC & NJ: Choosing Your Urban Partner

New York City and New Jersey's iconic skylines? They're pure proof of incredible construction and engineering. But peel back the layers of every towering building and complex industrial spot,...
Heavy equipment rigging during the installation of a new grain silo and processing system by R Baker.
Grain Silo & Equip. Installation: R Baker

R. Baker recently completed a challenging and uniquegrain processing installation, involving theheavy equipment riggingandindustrial equipment installationof four 70-foot processgrain silos, an...
Specialized healthcare demolition ensuring sterile environments with ICRA compliance.
Healthcare Demolition: ICRA Protocol & Clean Environments

Healthcare facilities present some of the most challenging environments for interior and selective demolition projects, where maintaining a sterile, contamination-free environment is absolutely...
lean construction meeting for Rigging NYC, NJ
Lean Construction: Optimize Demolition, Rigging & Dismantling Projects

Many R. Baker clients have adopted and use the lean construction process on their projects, the list includes most pharmaceutical companies, energy companies, manufacturing of all kinds along with...
Secure storage of industrial boiler for rigging and assembly projects in New York and New Jersey.
Rigging Services for NYC and NJ: Offsite Storage & Asset Management

For rigging projects in New York City and New Jersey, access to secure offsite storage and asset management is a crucial component of rigging, setting, and assembly operations,helping accommodate...
Safe rigging procedures and equipment inspection - R. Baker & Son
Rigging: A Complete Guide to Safety, Equipment, and OSHA Standards

Rigging is one of the most critical operations in heavy industry, and at R. Baker & Son, we specialize in safe, compliant lifting with the right equipment, planning, and OSHA-certified practices....
Workers in PPE during National Construction Safety Stand Down
Construction Safety Stand Down: History and Purpose

The Construction Safety Stand Down is an annual event aimed at raising awareness about safety in the construction industry, particularly focusing on fall protection. This initiative serves as a...
R. Baker & Son performing safe, sustainable rigging and demolition in NYC and NJ, with turnkey and MWBE-certified services
The Future of Rigging & Demolition in NY & NJ

The Evolving Landscape of Heavy Industrial Services in NYC & NJ R. Baker & Son stands as a cornerstone in the industrial services sector, with a profound legacy rooted in decades of...